Work in progress in Wroclaw

11-06-2018 @ 18:07

Work in progress in Wroclaw

Work in progress in Wroclaw! Extension of the railway siding in Kąty Wrocławskie has started. After the extension, the railway siding is going to have two tracks of the length of 600 m each. The facility is going to be able to serve even 4 trains a day. The area has been already levelled and the construction site infrastructure has been placed. The implementation is going to last for about 4 months. The Management Board of Schavemaker Invest assures that it is not the last investment connected with extension of the intermodal terminal in Kąty Wrocławskie - at present, a tender procedure for the next task entitled: ‘Extension of Roads and Yards together with the Rain Network on the Container Terminal in Kąty Wrocławskie’ is pending.